How did you spend your Holidays?

Posted by:

Did you take advantage of the Christmas season and take time off to relax, go on holidays or catch up with friends? Not us! For 8 weeks over December and January, the Kinvel Projects team was working on the total refurbishment of an existing Westpac branch.

This project incorporated a total refurbishment of Westpac Bank Cabramatta. The works included a full shut down of the branch over the Christmas period with a total demolition of the existing branch, including the removal of the existing asbestos timber flooring to the front half of the tenancy.

After the asbestos had been removed new structural supports were put in place for the concrete slab to be constructed. While these works were taking place the new fitout of the rear of the tenancy was happening. New mechanical services were installed, new security, new electrical, lighting was also installed.

New furniture was supplied throughout the branch. New floor finishes & painting works were carried out and the external façade of the branch was painted. Once the concrete works were completed the front of the tenancy fitout commenced. New signage was installed both internally and externally. The existing ATMs were removed and the new 24/7 zone was created to allow the customers to access the ATMs and coin exchange whenever they required. The existing shop front was removed to make way for a new entrance area, with new auto doors installed to allow for the new design of the 24/7 zone.

You can see more project photos and information on the website under Retail Projects.

If you have any refurbishment projects (with tight deadlines coming up), we would love to talk to you.